second floor is in, but just the floor

After Thursday’s storm, no work was done on Friday, Saturday, or Sunday. Things picked up again Monday, but I didn’t get out to the site until last night (Tuesday). We have the interior walls framed on the first floor. The metal beam in the garage is installed. Stairs to the second floor are built, and the deck is in place for the second floor. The missing first floor wall is framed, but not yet skinned with the Tyvek, and they’ve started setting up the rafters for the garage roof.